November 2001
Gas fired space heaters are installed in the roof
of the gridshell

December 2001
The scaffolding is removed and we have the first
glimpse of this amazing structure from the inside.

January 2002
The
classroom and the workshop (not shown) take shape under the gridshell.
February 2002
The lower sections are clad in softwood panelling.
Detail of the workshop and classroom roof
construction
Storage platform above the classroom
The flooring consists of ply then
sacrificial ash planks laid over the original timber deck.
March 2002
The interior of the workshop
space is completed and handed over to the Museum